How to Apply for a New Electricity Meter in Pakistan 2026 – Online Apply, Cost & Status Check
New Electricity Meter in Pakistan 2026
Getting a New Electricity Meter in Pakistan 2026 is now easier to understand with online application, application tracking, and digital updates. If you want to apply for a new electricity connection, you can follow the official process of your area’s electricity distribution company (DISCO) and check the latest requirements before submitting your application. Whether you live in Lahore, Multan, or another city, the process generally requires your CNIC, property ownership or occupancy documents, and other information requested by the relevant company. Applicants may also need to complete verification and pay the demand notice before the connection is installed. In this guide, you will learn how to apply for a new electricity meter online in Pakistan, check your application status, understand the required documents, and follow the latest 2026 connection procedure through official channels.
New Electricity Meter Application in Pakistan – What Changed from 2025 to 2026?
There is an important difference between the older perception of the “WAPDA meter application” and the actual system used today.
Many people still search for WAPDA meter online apply, but electricity distribution to consumers is handled by individual distribution companies rather than by one single nationwide consumer application office. The current NEPRA Consumer Service Manual states that applications can be submitted in person or online through the relevant DISCO, and applicants receive an acknowledgement with a serial number, tracking ID or case ID.
The updated Consumer Service Manual was issued by NEPRA on November 26, 2025, incorporating earlier amendments and clarifications. It applies to the distribution companies and provides the framework for applications, documents, charges, meter installation and service timelines.
So, in 2026, the practical process is:
Select your DISCO → prepare documents → submit the application → receive tracking/case ID → verification/site process → demand notice → payment → meter installation and energization.
The system is also moving further toward digital processing. PITC describes the Electricity New Connection system as supporting online new-connection applications, online tracking, demand-notice payment integration and SMS alerts as an application moves through different stages.
Also Read ; FESCO Bill Online Check 2026
How to Apply for a New Electricity Meter in Pakistan?
If you want to know how to apply for a new electricity meter in Pakistan, start by identifying the electricity distribution company responsible for your property.
The first step is not to search for a generic “WAPDA connection.” Instead, identify whether your property falls under LESCO, MEPCO, FESCO, IESCO, GEPCO, PESCO, HESCO, SEPCO, QESCO, TESCO, HAZECO or another applicable electricity supplier.
Once the correct company is identified, you can use its new-connection facility or the relevant Electricity New Connection system where available.
The NEPRA Consumer Service Manual confirms that the prescribed application and power supply contract forms are available from DISCO offices and on the DISCO website. Applications may be submitted personally or online with the required supporting documents.
Basic application process
- Identify your electricity distribution company.
- Select the appropriate connection type and load.
- Prepare your CNIC and property-related documents.
- Complete the new connection application.
- Upload or submit the required documents.
- Submit the application through the available online or office channel.
- Save the acknowledgement, tracking ID or case ID.
- Complete any verification or site-survey requirements.
- Receive the demand notice when issued.
- Pay the applicable charges through the permitted channel.
- Wait for the connection and meter installation according to the applicable timeline.
The exact requirements can vary according to the type of property, connection category, load and local DISCO procedure.

How Can I Apply for a New Electricity Meter Online in Pakistan?
For applicants searching how can I apply for a new electricity meter online in Pakistan, the important thing is to use the official electricity distribution system rather than an unofficial website or agent.
The Electricity New Connection system is designed to allow consumers to submit applications and subsequently track them. Official PITC information describes ENC as a web-based system for online new-connection applications, tracking and related processing.
The official ENC system also provides functions such as Home, Track, Apply, Change and Print Form, depending on the user and DISCO access.
After submitting an online application, keep the tracking or case number safely. The NEPRA manual specifically states that the applicant receives a serial number/tracking ID/case ID after receipt of the application.
offichail website ; https://enc.com.pk/
How to Get a New Electricity Connection in Pakistan?
The question how to get a new electricity connection in Pakistan is slightly different from simply asking how to obtain a physical meter.
The electricity company first has to determine whether the premises and application meet the applicable eligibility and technical requirements. The application can then move through document verification, site survey, service-cost estimation, demand notice, payment and installation.
A new meter cannot normally be treated as an immediate retail purchase. It is part of a regulated electricity connection process.
The Consumer Service Manual covers the application procedure, required documents, connection charges, meter installation and time frames.
How to Apply for a New Electricity Meter by CNIC?
A common search is how to apply for a new electricity meter by CNIC.
Your CNIC is an important identification document, but a CNIC number by itself does not replace the complete new-connection application. The applicant may need identity documents, ownership or occupancy-related evidence and other documents depending on the case.
For online applications, the CNIC information helps identify the applicant, while the property and technical information establishes where the connection is required.
The 2025 revised CSM also makes clear that applications can require supporting documents and that DISCO may ask for original or attested documents for verification before energization when the application was submitted through a mode other than in person.
Therefore, be careful with websites or individuals claiming that a new meter can be issued simply after entering a CNIC number.
Can I Apply for a New Electricity Meter Online?
Yes, online submission is available under the applicable DISCO process.
The NEPRA Consumer Service Manual expressly provides that applications with supporting documents may be submitted in person or online through the DISCO website. After receiving the application, the DISCO issues an acknowledgement and tracking/case ID.
However, online submission does not mean every part of the process happens without physical verification. Depending on the application, the applicant may still have to provide original or attested documents or complete technical verification before the connection is energized.
WAPDA Meter Online Apply – What Does It Actually Mean?
People commonly type WAPDA meter online apply into Google because “WAPDA meter” has become a familiar phrase in Pakistan.
For a new domestic electricity connection, however, it is more accurate to identify the relevant distribution company. The consumer-facing process is generally handled through the applicable DISCO rather than through a single generic WAPDA consumer application.
This distinction matters because your application, demand notice, service estimate, installation and tracking are connected to the company responsible for electricity distribution in your area.
In other words, instead of asking only “Where can I apply for a WAPDA meter?”, first ask:
Which DISCO supplies electricity to my property?
That will take you to the correct application route.
Documents Required for a New Electricity Meter
Applicants frequently ask what documents are required for a new electricity meter. The exact list depends on the connection and property, but the official framework requires supporting documentation with the application.
Common documents can include:
| Document / Requirement | Why it may be required |
|---|---|
| Applicant CNIC | Identification of the applicant |
| Ownership proof | Establishes the applicant’s connection with the premises |
| Application form | Official request for electricity service |
| Power Supply Contract | Required connection agreement |
| Wiring Test Report | Technical safety/installation verification where applicable |
| NOC / approved plan | Required in certain property or development situations |
| Landlord/owner authorization | Relevant where the applicant is not the owner |
| Other supporting documents | Depending on connection type and DISCO requirements |
The CSM states that the applicant must attach the required supporting documents, while additional documents can be requested if necessary.
Is an approved map or NOC always required?
No.
The 2025 revised CSM contains several situations where an approved map, site plan, layout plan or NOC is not required, including certain additional connections and premises located inside approved housing schemes or societies. There are also specific exceptions for rural areas, old colonies and other situations.
This is important because old online articles sometimes present NOC requirements as if they apply to every applicant. They do not.
How to Apply for a New LESCO Electricity Meter?
If your property is in the LESCO service area, the question becomes how to apply for a new LESCO electricity meter.
The process follows the same basic regulatory framework but is handled by LESCO for its service territory. You should use the official LESCO/ENC route available for your area, submit the required documents and retain your application tracking information.
For Lahore applicants, it is particularly important to avoid confusing a general “WAPDA” search with the actual LESCO process.
LESCO is also continuing to introduce digital metering technology. In July 2026, Dawn reported that LESCO had started a phased programme to replace conventional single-phase meters at Punjab government departments with AMI smart meters, with 1,000 meters planned in the first phase and 8,342 conventional single-phase non-AMI meters identified in the relevant government departments within LESCO’s service area.
This development shows the wider direction of electricity metering toward more digital systems, although it should not be interpreted as meaning that every new residential customer will automatically receive an AMI meter.
How to Apply for a New Electricity Meter in Lahore?
For someone searching how to apply for a new electricity meter in Lahore, LESCO is normally the key distribution company to check, depending on the exact location.
The applicant should first confirm that the property falls within LESCO’s service territory. Then the new-connection application can be submitted through the applicable official channel.
The basic sequence remains:
LESCO service area → application → documents → tracking ID → verification → demand notice → payment → connection installation.
Do not pay an unofficial agent simply because they claim they can “speed up” the meter process. Use the official application and payment channels and keep receipts for every payment.
How to Apply for a New MEPCO Electricity Meter?
For people searching how to apply for a new MEPCO electricity meter, the process is handled through MEPCO for properties within its service territory.
MEPCO consumers should use the applicable official new-connection channel and follow the documentation and verification requirements for their property.
PITC’s current information indicates that some MEPCO consumers may also be directed toward the Power Smart app or a customer facilitation centre for certain services, depending on the type of application and area.
This is another reason why applicants should check the latest official instructions rather than relying on a 2024 or 2025 blog post.
New Electricity Meter Connection Cost in Pakistan 2026
One of the most important questions is how much does a new electricity meter connection cost in Pakistan?
There is no single nationwide flat price that applies to every new meter.
The final amount depends on factors such as the connection category, sanctioned load, applicable capital or connection cost, security deposit, site conditions and the work or material required.
Under the revised CSM, connection charges are payable according to rates approved under the applicable regulatory framework. The DISCO subsequently issues demand notices for capital cost/connection charges and security deposit.
The 2025 CSM lists the following security-deposit rates:
| Consumer category | Security deposit |
|---|---|
| Residential A-1 Urban | Rs 1,220 per kW |
| Residential A-1 Rural | Rs 610 per kW |
| Commercial A-2 Urban | Rs 1,810 per kW |
| Commercial A-2 Rural | Rs 920 per kW |
| Industrial B1 | Rs 1,580 per kW |
| Industrial B2 | Rs 2,010 per kW |
| Industrial B3 | Rs 2,890 per kW |
| Industrial B4 | Rs 3,560 per kW |
| General Services A-3 | To be determined by NEPRA |
These figures are security-deposit rates, not the complete cost of obtaining a new electricity meter. Capital/connection charges and other applicable amounts can be included in the demand notice.
Therefore, a website claiming that every applicant will pay exactly the same “new meter fee” should be treated cautiously.
How Does the Demand Notice Work?
After the application is processed, the DISCO calculates the applicable charges and issues the demand notice.
According to the revised CSM, demand notices for capital cost/connection charges and security deposit can be sent through registered post, courier or online, and an applicant can also download the demand notice from the DISCO website using the serial number, tracking ID or case ID where that facility is available.
The normal payment period specified in the CSM is 30 days. A further 30-day grace period may be allowed upon request, provided the request is submitted at least three days before the original payment deadline.
This is an important detail for applicants because receiving the demand notice is not the final stage. The connection installation process proceeds after the required payment is made.
How Long Does It Take to Get a New Electricity Meter?
People often ask how long does it take to get a new electricity meter.
The answer depends on the sanctioned load and connection category.
For a normal connection of up to 15 kW at 400 volts, the revised CSM gives a total processing timeline of 30 days. The stages include application registration/site survey, preparation and issuance of the demand notice, work-order/material execution and meter installation.
For higher loads, the timeline increases:
| Connection category | Load / voltage | Official CSM timeline |
|---|---|---|
| Category 1 | Up to 15 kW at 400 V | 30 days |
| Category 2 | Above 15 kW to 70 kW at 400 V | 44 days |
| Category 3 | Above 70 kW to 500 kW at 400 V | 58 days |
| Category 4 | Above 500 kW to 5,000 kW at 11/33 kV | 106 days |
| Category 5 | All loads at 66 kV and above | 496 days |
These are the time frames stated in Annexure III of the revised CSM.
For a normal household, the up-to-15-kW Category 1 timeframe of 30 days is generally the most relevant figure, assuming the application is complete and the applicable requirements are fulfilled.
How to Check New Electricity Meter Application Status Online?
After submitting the application, applicants should keep their tracking ID or case ID.
If you want to know how to check new electricity meter application status online, use the tracking facility provided by the relevant electricity distribution company or ENC system.
PITC’s ENC documentation specifically describes online application-status tracking and SMS alerts as part of the system.
The official CSM also confirms that the applicant is given a serial number/tracking ID/case ID and that the demand notice can, where available, be downloaded using that identification number.
What if the status is not updating?
Do not immediately submit another application.
First check the application number, verify whether additional documents have been requested and contact the relevant DISCO customer service centre if the application remains unchanged for an unusually long period.
Keeping your acknowledgement and payment receipts is especially important if you later need to raise a complaint.
How to Check New Meter Connection Status by CNIC?
Another common search is how to check new meter connection status by CNIC.
The important distinction is that the official process generally relies on the application’s tracking ID, serial number or case ID, rather than treating the CNIC alone as the universal tracking number.
Your CNIC identifies you as the applicant, but once the application is submitted, save the tracking/case number given by the electricity company.
If an official DISCO portal specifically offers a CNIC-based lookup, follow that portal’s instructions. Otherwise, use the application ID provided at submission.
How to Check Electricity Meter Application Status Online?
The process for how to check electricity meter application status online is straightforward once you have retained your application information.
Open the official tracking facility of your electricity distribution company, enter the required tracking/application details and review the current stage.
A typical application can move through stages such as application receipt, document verification, site survey, estimate/demand notice, payment, work order and meter installation.
The exact wording of the status can vary between DISCO systems, so applicants should focus on the stage shown rather than expecting every company to use identical terminology.
How to Apply for a New Electricity Meter in Urdu?
For consumers searching how to apply for a new electricity meter in Urdu, the procedure is the same, but applicants can use the Urdu application forms where provided.
The NEPRA CSM says that the prescribed application and power supply contract forms are available in both English and Urdu.
If you are not comfortable completing the application yourself, DISCO staff are required under the CSM to provide assistance or information regarding completion of the application form at the office where the form is submitted.
This is safer than handing your CNIC documents to an unknown agent.
What Happens After You Submit the Application?
Submitting the form is only the beginning.
For a standard new connection, the DISCO reviews the application and supporting documents. A site survey and wiring-test verification can form part of the process, after which the service cost estimate and demand notice are prepared.
Once the demand notice has been paid, the connection proceeds toward installation and energization according to the applicable CSM timeframe.
For Category 1 connections up to 15 kW, the 30-day timeline is divided into 4 days for application/site-survey related processing, 6 days for estimate and demand notice, 11 days for work-order/material execution and 9 days for metering installation.
This breakdown is useful because it shows why the process cannot always be completed immediately after an online application.
What If the Electricity Company Delays the Connection?
The CSM does not simply ignore delays.
Its Annexure III states that when a distribution company does not take the required action within the stipulated time, it has to provide reasons for each day of delay in writing to the consumer, with a copy to NEPRA. The delay does not remove the DISCO’s obligation to complete the required action.
If an applicant believes that the case has been unnecessarily delayed, the first practical step is to contact the relevant DISCO and keep evidence of the application, tracking number, demand-notice payment and previous complaints.
If the matter remains unresolved, NEPRA provides an official Consumer Complaint Management System for electricity consumers.
2026 Important Update: Smart and Digital Metering
Electricity metering in Pakistan is gradually becoming more digital.
In July 2026, LESCO announced a phased replacement of conventional single-phase meters at Punjab government departments with Advanced Metering Infrastructure (AMI) smart meters. The reported first phase involved 1,000 meters, while the relevant LESCO data identified 8,342 conventional single-phase non-AMI meters at Punjab government departments.
This is an important 2026 development, but consumers should not assume that every ordinary new residential connection will automatically receive the same type of smart meter.
The actual meter and connection arrangement depend on the applicable DISCO, approved standards, technical requirements and the connection being provided.
What Should Applicants Expect in 2027?
For 2027, the biggest point to watch is not a confirmed nationwide new-meter fee or a completely new application process.
NEPRA’s official website shows that amendments to the Consumer Service Manual were still being considered in 2026, including a public notice issued on September 25, 2026 seeking comments on proposed CSM amendments.
Therefore, consumers applying in 2027 should check the latest NEPRA and DISCO instructions before submitting an application.
The overall direction is clear: online applications, digital tracking, electronic communication and smarter metering are becoming increasingly important. But any proposed 2027 policy should only be treated as final after NEPRA officially notifies it.
Important 2026 Notes for New Electricity Meter Applicants
Do not confuse WAPDA with your actual DISCO. The relevant distribution company depends on your location.
Do not rely on CNIC alone. A CNIC identifies the applicant, but the application normally requires supporting documents and property-related information.
Save your tracking ID. It can be important for checking progress and accessing the demand notice.
Do not assume there is one fixed new-meter price. The final demand depends on applicable connection charges, security deposit, load and other requirements.
Check the demand notice carefully. The CSM provides a normal 30-day payment period and a possible additional 30-day grace period upon request under the stated conditions.
Use official payment channels. Keep the payment receipt as proof.
Do not pay unofficial agents for guaranteed approval. An agent cannot replace the regulatory and technical requirements of the DISCO.
Check the latest rules before a 2027 application. NEPRA was still considering CSM amendments during 2026, so older articles should not automatically be treated as current policy.
Final Answer: New Electricity Meter Application in Pakistan 2026
The process of getting a new electricity meter in Pakistan has become more structured and increasingly digital. In 2026, consumers can submit new-connection applications online where the applicable DISCO system supports it, receive a tracking or case ID, follow the application, receive a demand notice and make the required payment before the connection is installed.
For an ordinary connection of up to 15 kW at 400 V, the current revised CSM provides a 30-day connection timeline, while higher-load categories have longer prescribed timelines.
The most important advice is to use the official DISCO/ENC channel, submit accurate documents, keep the tracking ID and payment receipts, and verify any new 2027 requirements directly from NEPRA or the relevant electricity company.